This section serves as a checklist to make sure your Horizon DaaS 9.2.x platform has everything necessary for a successful deployment.
-
Required Files
-
Automation Appliances
-
Horizon Version Manager (HVM):
Horizon-Version-Manager-22.1.0.0-21662925_OVF10.ova -
Horizon Air Link (HAL)
horizon-air-link-22.1.0.0-21661035_OVF10.ova
-
-
Appliance Template
`ApplianceTemplate_22_1_0_20230409_signed.ova```
Note: If you want to change the default password on the template, perform the following steps:
- Deploy
ApplianceTemplate_22_1_0_20230409_signed.ovain vCenter. - Power on the VM and change the appliance password to the password you want to use.
- Export and download to a new OVA file. Use this file for all future deployments.
- Deploy
-
Platform
av-manager-2303.0.0-65-airBAT.debdbmonitor_22.1.0.debdt-aux-22_1_0.debdt-platform-22_1_0.deblatest_rev.txtnode-manifest.jsonwem-service-diagnose-19.3.24.debxmp-2303.0.0-2907-airBAT.deb
-
Agents
-
Latest compatible version of Horizon Agents Installer (HAI). See the Omnissa Product Interoperability Matrices.
Note: If you are using a “hot patch” style Agent Automatic Update, you also need the related
agent.tarfile. -
Latest compatible version of Unified Access Gateway (UAG). See the Omnissa Product Interoperability Matrices.
-
Latest compatible version of Dynamic Environment Manager (DEM). See the Omnissa Product Interoperability Matrices.
-
-
Utilities
- WinSCP
- 7zip or WinZip
-
-
vCenter Server and vSphere Hypervisor (ESXi) Requirements
-
Latest compatible versions of vCenter Server and vSphere. See the Omnissa Product Interoperability Matrices.
-
Distributed Resource Scheduler (DRS) set to
offormanual -
One or more vCenter Server appliances
Note: To use a single vCenter Server configuration, you must set the
allow.shared.hostmanagerpolicy totrue. You are prompted to do this at the end of each set of installation and upgrade steps. -
Individual ESX Host mapping is not supported.
-
-
Networking
-
Front end/management network created and IPs designated to SP appliances.
-
BBLL (Backbone Link Local) network created and IPs designated to SP appliances.
-
IP ranges planned to accommodate your maximum appliance estimate.
For example, if you plan on accommodating 200 total appliances, a /24 mask gives you a maximum of 254 usable IP addresses. Because you need approximately 400 IPs across 200 appliances (primary/standby), consider using a /23 mask instead.
-
One network type used across all appliances (Standard Switch VLAN, vDS VLAN, or VXLAN)
-
All required network visibility, routing, hardening, and so on, must be configured ahead of time.
-
The gateway used for the Service Provider network must have ICMP echo enabled. This is required for HVM deployment tasks.
-
-
Storage
- Datastores provisioned and allocated for service providers and tenants
- All platform files and templates available in a file share accessible to the service provider and tenant
-
Active Directory
- Domain Controllers configured to Microsoft Best Practices
- Domain Controller IP addresses and port requirements
- NTP is properly configured and time sync is active and current.
- Domain Controllers are on the same network.
- Computer and User OUs, Admin Groups, User Groups, Computer/User GPOs
- Permissions configured
Password never expiresaccount option selected- Domain Bind account with adequate permissions
- Full Distinguished Name
- DNS
- Hostnames, IPs, and open ports
- Scavenging settings
- Conditional Forwarding (for proper communication between service providers and data centers)
- DHCP (static IP addressing- DHCP not required)
- Domain Controllers configured to Microsoft Best Practices
-
Service Provider Requirements
Note: All platform appliances must set the timezone to UTC only.
-
Horizon DaaS version required for upgrade to Horizon DaaS 9.2.0
Service provider must be running Horizon DaaS 9.0.x or 9.1.x.
-
-
Tenant Requirements
-
Horizon DaaS version required for upgrade to Horizon DaaS 9.2.0
All tenants must be running Horizon DaaS 9.0.x or 9.1.x.
Note: All Debian packages for the version you are running must be available in the service provider appliance's
/data/repo folder. -
Appliance Location in vCenter for upgrade to Horizon DaaS 9.2.0
For upgrade to Horizon DaaS 9.2.0, all appliances must be in the root folder of vCenter.
Note: If appliances are not in the root folder, you might need to move them there.
-
Network
- If you are using Instant Clone desktops, you cannot use VLANs. IC desktops require DVS port groups or VXLANs to function properly.
- All virtual machines (appliances, utility servers, images, and so on) must be using VMXNET3 network adapters. E1000 network adapters are not supported.
-
VPN
- Bandwidth requirements
- PSK, endpoint IPs
-
UAG
See information in the Tenant Installation Worksheet.
-
Active Directory
-
Domain Controller IP addresses, port requirements
-
Computer and User OUs, Admin Groups, User Groups, Computer/User GPOs created
- Horizon View, UEM,
*.admx, and*.admlfiles downloaded - Import procedure
- Service Accounts have
Password never expiresaccount option selected
- Horizon View, UEM,
-
Domain Join account with adequate permissions
- Full Distinguished Name
-
Domain Bind account with adequate permissions
- Full Distinguished Name
-
NTP properly configured and time sync active and current
Note: Sysprep/Generalize cloned server images each time to avoid domain join issues.
-
-
DHCP Server
- Defined Scopes, reservations, and so on
- Lease time for scopes set at eight hours instead of the default eight days
-
DNS Server
- Hostname, IPs
- Proper DNS record scavenging configuration
-
File Server
- General File sharing and permissions configured
- HAI installer and
Agent.tarfile accessible on the file share
-
Images
- VM hardware version up to date
- VMware Tools up to date
- Proper agent versions for this version of Horizon DaaS (Horizon Agent Integrated Agent, UEM, and so on)
- Image optimized (OptimizeanImage.md))
-
Workspace ONE UEM
- Workspace ONE UEM shares created and configured
- Workspace ONE UEM installed and configured on the designated server
- Workspace ONE UEM initial configuration complete
- GPO configuration and linking to Computer OUs complete
-
-
Compute Resources
-
If you are upgrading an existing environment, confirm that each desktop manager is configured with only one compute resource. Multiple compute resources per desktop manager are not supported.
Note: Any offline or deactivated tenant organizations must be deleted from the platform or reconfigured with a single compute pool.
-
No stand-alone ESXi hosts in the existing compute pools.
-
-
File Integrity Verification
To ensure a successful, issue-free installation, verify that the core installation files have the correct checksum before you start. See Verify File Integrity.
Was this page helpful?